In the first section of building 1, the vertical of the 18th floor is performed
RIEL Real Estate Corporation reports that the builders continue construction of building 1 of OK'Land RC. Now in the first section, the vertical of the 18th floor is being carried out, the walls are laid on the sixth, seventh, and eighth floors.
In the second section, the formwork of the floor slab of the 19th floor is being installed, the laying on the sixth, seventh, and eighth floors.
Besides, according to RIEL employees, in the third section, reinforcement and concreting of the floor slab of the 19th floor and masonry on the 11-13th floors are underway. As far as the fourth section is concerned, reinforcement and concreting of the floor slab of the 19th floor is carried out, masonry is performed on the 11-13th floors.