Menu
To the news list

In the first section of building 1, the vertical of the 18th floor is performed

September 02, 2021

RIEL Real Estate Corporation reports that the builders continue construction of building 1 of OK'Land RC. Now in the first section, the vertical of the 18th floor is being carried out, the walls are laid on the sixth, seventh, and eighth floors.

In the second section, the formwork of the floor slab of the 19th floor is being installed, the laying on the sixth, seventh, and eighth floors.

Besides, according to RIEL employees, in the third section, reinforcement and concreting of the floor slab of the 19th floor and masonry on the 11-13th floors are underway. As far as the fourth section is concerned, reinforcement and concreting of the floor slab of the 19th floor is carried out, masonry is performed on the 11-13th floors.

You can find out more about the terms of purchasing an apartment in OK'Land RC and the progress of the complex construction in our sales departments, the addresses are available at the link.

We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.
Subscribe to news and promotions
Thank you for subscribing to our newsletter!
Constructors

Kyivmetbudinvest

Join our social networks
Contact us in convenient way
(044) 499-96-51
Feedback
The exchange rate as of 11/26/2024 is 41.43 UAH.
Sales departments
Kyiv, str. Konovaltsya, 30
Kyiv, 56, Ukrainian Air Force avenue
© 2024  Оk'Land. All rights reserved.Privacy policy
Made in WEZOM
This site uses cookies for more comfortable work of the user. By continuing to browse the site, you agree to the use of cookies.