Internal engineering networks are being installed in the third stage

December 06, 2024

In the first building of the third stage of Ok’Land RC, active work continues on the arrangement of internal engineering networks, including water supply, sanitation, heating and electricity, which are 91% complete.

The façade insulation is nearing completion, the installation of apartment radiators is 95% complete, and the installation of elevators is also underway.

Finishing of common areas and staircases is 88% complete, installation of technical doors is 95% complete. Work continues on the installation of switchboard hatches and smoke exhaust valves, which are 90% complete. The basement utilities, including the electrical room, individual heating unit, pumping station and ventilation, are 92% complete. The landscaping of the adjacent territory is currently 50% complete.

Each stage of construction brings us closer to the moment when future residents will be able to enjoy the comfort of their new homes. More information on the progress of work and terms of purchase is available in the sales departments – contacts are available here.

We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.
Subscribe to news and promotions
Thank you for subscribing to our newsletter!
Constructors

Kyivmetbudinvest

Join our social networks
Contact us in convenient way
(044) 499-96-51
Feedback
The exchange rate as of 12/27/2024 is 42.08 UAH.
Sales departments
Kyiv, str. Konovaltsya, 30
Kyiv, 56, Ukrainian Air Force avenue
© 2024  Оk'Land. All rights reserved.Privacy policy
Made in WEZOM
This site uses cookies for more comfortable work of the user. By continuing to browse the site, you agree to the use of cookies.