Menu
To the news list

In all sections of building 2, basements are being finished

September 02, 2021

RIEL Real Estate Corporation reports that the builders continue construction of building 2 of Оk’Land RC. Basements and common facilities are being finished in all sections, electrical work is in progress. This was reported by the builders.

It is also reported that the screeds are performed on floors 3-15 in the second section, on floors 3-17 in the third section, and on floors 3-24 in the fourth section.

You can find out more about the terms of purchasing an apartment in OK'Land RC and the progress of the complex construction in our sales departments, the addresses are available at the link.

We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.
Subscribe to news and promotions
Thank you for subscribing to our newsletter!
Constructors

Kyivmetbudinvest

Join our social networks
Contact us in convenient way
(044) 499-96-51
Feedback
The exchange rate as of 5/4/2024 is 39.6 UAH.
Sales departments
Kyiv, 56, Ukrainian Air Force avenue
© 2024  Оk'Land. All rights reserved.Privacy policy
Made in WEZOM
This site uses cookies for more comfortable work of the user. By continuing to browse the site, you agree to the use of cookies.