In the third stage, a monolithic retaining wall is being constructed

December 08, 2023

Real Estate Corporation RIEL reports that the строители продолжают возведение жилого комплекса Ok’Land. In the third stage, a monolithic retaining wall is being constructed.

It is also reported that in house No. 2, the roof is 95% complete, the waterproofing of sections 1, 2, 3, 4 is 100% complete; the installation of windows and balcony doors is 97% complete, and work continues on the installation of windows and stained glass windows on the first floors. The blockwork is 100% complete; work on the arrangement of exterior water supply and sewerage networks is 80%  ready. In sections 1, 3, 4, the installation of internal engineering networks (water supply, sewerage, heating, and electricity mains) is being performed; readiness is 20%. Insulation of the facade is in progress, 45% completed.

In parking lot No. 2, installation of utility networks (electricity, water supply, and sewerage), fire extinguishing and smoke removal systems is underway.

You can find out more about the construction progress and the sales terms for purchasing apartments in Ok'Land RC in our sales department, contacts are here.

We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.
Subscribe to news and promotions
Thank you for subscribing to our newsletter!
Constructors

Kyivmetbudinvest

Join our social networks
Contact us in convenient way
(044) 499-96-51
Feedback
The exchange rate as of 11/22/2024 is 41.37 UAH.
Sales departments
Kyiv, str. Konovaltsya, 30
Kyiv, 56, Ukrainian Air Force avenue
© 2024  Оk'Land. All rights reserved.Privacy policy
Made in WEZOM
This site uses cookies for more comfortable work of the user. By continuing to browse the site, you agree to the use of cookies.