In the third stage, the screed is 40% complete in all sections

January 12, 2024

Real Estate Corporation RIEL reports that the construction of Ok’Land residential complex is in progress. In the third stage, in all sections the screed is 40% complete, installation of windows and stained-glass windows of the first floors continues, work is ongoing to lay external water supply and sewerage systems. The monolithic supporting wall has been completed.

In the parking lot No. 2, the utility networks (power supply, water supply, sewerage), fire-fighting and smoke-extinguishing systems are being laid. Water drainage chutes are being installed.

Fire extinguishing system is being installed in the parking lot No.1.

You can find out more about the construction progress and the conditions for selling apartments in Ok’Land RC in our sales department, contacts are here.

We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.
Subscribe to news and promotions
Thank you for subscribing to our newsletter!
Constructors

Kyivmetbudinvest

Join our social networks
Contact us in convenient way
(044) 499-96-51
Feedback
The exchange rate as of 11/21/2024 is 41.35 UAH.
Sales departments
Kyiv, str. Konovaltsya, 30
Kyiv, 56, Ukrainian Air Force avenue
© 2024  Оk'Land. All rights reserved.Privacy policy
Made in WEZOM
This site uses cookies for more comfortable work of the user. By continuing to browse the site, you agree to the use of cookies.