Finishing works of the common facilities continue on the third stage
October 10, 2024
The construction of the third stage of Ok’Land RC continues actively. At present, the finishing of common areas and staircases is 80% complete.
Below is an update on the status of other works:
- Façade insulation – 95% complete.
- Installation of internal engineering networks (water supply, sanitation, heating, electricity) – 87% complete.
- Installation of elevators – 95% complete.
- Installation of apartment doors is 98% complete, technical doors – 80% complete.
- Installation of utilities in the basement – 65% complete.
- Installation of switchboard hatches and smoke exhaust valves – 50% complete.
- Basement utilities (electrical room, individual heating unit, pumping station, ventilation) – 72% complete.
- External water supply and sanitation networks – 96% completed.
- Improvement of the adjacent territory – 30% completed.