Finishing works of the common facilities continue on the third stage

October 10, 2024

The construction of the third stage of Ok’Land RC continues actively. At present, the finishing of common areas and staircases is 80% complete.

Below is an update on the status of other works:

  • Façade insulation – 95% complete.
  • Installation of internal engineering networks (water supply, sanitation, heating, electricity) – 87% complete.
  • Installation of elevators – 95% complete.
  • Installation of apartment doors is 98% complete, technical doors – 80% complete.
  • Installation of utilities in the basement – 65% complete.
  • Installation of switchboard hatches and smoke exhaust valves – 50% complete.
  • Basement utilities (electrical room, individual heating unit, pumping station, ventilation) – 72% complete.
  • External water supply and sanitation networks – 96% completed.
  • Improvement of the adjacent territory – 30% completed.

For more information on the construction progress and terms of sale, contact the sales departments, please follow the link.

We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.
Subscribe to news and promotions
Thank you for subscribing to our newsletter!
Constructors

Kyivmetbudinvest

Join our social networks
Contact us in convenient way
(044) 499-96-51
Feedback
The exchange rate as of 10/22/2024 is 41.26 UAH.
Sales departments
Kyiv, str. Konovaltsya, 30
Kyiv, 56, Ukrainian Air Force avenue
© 2024  Оk'Land. All rights reserved.Privacy policy
Made in WEZOM
This site uses cookies for more comfortable work of the user. By continuing to browse the site, you agree to the use of cookies.