Power supply and lighting networks in parking lot No. 1 are 40% complete
October 10, 2024
RIEL Real Estate Corporation reports about the active process of construction of the Ok’Land Residential Complex.
Currently, the installation of networks is underway in parking lot No. 1:
- Power supply and lighting networks are 40% complete.
- Installation of the warning system is 50% complete.
- Installation of ventilation ducts has begun – 3% complete.
- Installation of fire gates and technical doors – 2% completed.