RIEL Real Estate Corporation reports that the builders continue the construction of the Ok’Land Residential Complex. At present, the smoke removal system in parking lot No. 2 is 99% ready, finishing works and arrangement of the electrical switchboard are 90% complete.

Utility networks (electricity, water supply, sanitation) and lighting are 99% complete. The screed has been fully completed, and gates and doors have been installed. The parking lot has also been marked and wheel chocks installed, and the pumping station is 100% complete.

In parking lot No. 1, the laying of drainage trays on the ground floor is underway. The fire extinguishing system is 82% complete, the public address system is 50% complete, and the laying of water supply and sewerage networks has also begun. The installation of power supply and lighting networks continues.

You can find out more about the construction progress and terms of sale of apartments in Ok’Land RC in our sales department, please follow the link.

We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.
Subscribe to news and promotions
Thank you for subscribing to our newsletter!
Constructors

Kyivmetbudinvest

Join our social networks
Contact us in convenient way
(044) 499-96-51
Feedback
The exchange rate as of 12/3/2024 is 41.66 UAH.
Sales departments
Kyiv, str. Konovaltsya, 30
Kyiv, 56, Ukrainian Air Force avenue
© 2024  Оk'Land. All rights reserved.Privacy policy
Made in WEZOM
This site uses cookies for more comfortable work of the user. By continuing to browse the site, you agree to the use of cookies.