In the first section of house No.1, the 22d floor vertical is performed
RIEL Real Estate Corporation reports that the builders are busy constructing the house No. 1 of OK'Land residential complex. Now in the first section, a vertical of 22nd floor is performed, the walls are laid on the 12th floor.
The second section has the 22nd floor slab cast, the masonry is performed on the 11th floor.
Besides, according to RIEL employees, in the third section, reinforcement and concreting of the floor slab of the 23rd floor is underway, the masonry is performed on the 15th floor. And in the fourth section, a vertical of 23 floors is performed, masonry is 15-16 floors.