In the first section of house No. 1, the vertical of the 13th floor is performed
RIEL Real Estate Corporation reports that the builders continue erection of house No. 1 of Ok'land Residential Complex. Now in the first section, the vertical of the 13th floor is being performed, the walls are laid on the 4th and 5th floors.
In the second section, the pouring of the floor slab of the 16th floor has been completed.
Also, according to RIEL employees, the vertical of the 17th floor is poured in the third section, the laying continues on the 9-11th floors. And in the fourth section, the formwork of the floor slab of the 17th floor is mounted, the laying is underway on the 10th floor.