Ok’Land RC: façade works in the third stage are underway
The third stage of the Ok’Land RC is steadily approaching completion. As of today, the façade insulation is 96% complete, and the finishing of common areas and staircases is 87% complete.
The internal engineering networks (water supply, sanitation, heating, electricity) are 89% complete, and the elevators are 96% complete.
Installation of doors is also in its final stage: apartment doors are 99% installed, technical doors – 89%. In the basement, utilities are 85% complete, and external water supply and sewerage networks are 97% complete.
Works on the improvement of the adjacent territory are ongoing and are currently 40% complete.
Each stage of construction brings us closer to the moment when future residents will be able to enjoy the comfort of their new home. For more information on the construction progress and sales conditions, please contact our sales departments – contacts are available at the link.