Facade works are being performed in the third stage
August 09, 2023
RIEL Real Estate Corporation reports that the builders are actively work on the construction of Ok'Land RC. In the house No. 1 of the third stage, facade works are being performed: mineral wool wall insulation. The internal networks of the house are being laid, and the installation of a fire-fighting system has also started.
Is is also reported that the installation of elevator equipment is underway and the work on waterproofing the upper slab of the parking lot is being completed.